Golden Quadrilateral

Golden Quadrilateral
Highway map of India with the Golden Quadrilateral highlighted in solid blue colour
Route information
Maintained by NHAI
Length5,846 km (3,633 mi)
ExistedJuly 2013; 10 years ago (July 2013)–present
KolkataDelhi
Length1,453 km (903 mi)
Major intersections NH 44 & NH 19
DelhiMumbai
Length1,419 km (882 mi)
Major intersections NH 48
MumbaiChennai
Length1,290 km (800 mi)
Major intersections NH 48
ChennaiKolkata
Length1,684 km (1,046 mi)
Major intersections NH 16
Location
CountryIndia
Highway system
VijayawadaGuntur Expressway section of NH-16
A section of the Golden Quadrilateral highway from Chennai–Mumbai phase
NH46: Bengaluru–Chennai section of India's 4-lane Golden Quadrilateral highway
NH 16 another section of Golden Quadrilateral highway in Visakhapatnam on the Kolkata–Chennai section
Kolkata–Durgapur section of India's GQ highway
NH4: Chennai–Mumbai section of the GQ highway near Krishnagiri, Tamil Nadu

The Golden Quadrilateral (Hindi: स्वर्णिम चतुर्भुज, romanizedSvarnim Chaturbhuj; abbreviated GQ) is a national highway network connecting several major industrial, agricultural and cultural centres of India. It forms a quadrilateral with all the four major metro cities of India forming the vertices, viz., Delhi (north), Kolkata (east), Mumbai (west) and Chennai (south). Other major cities connected by this network include Ahmedabad, Bengaluru, Balasore, Bhadrak, Bhubaneswar, Cuttack, Berhampur, Durgapur, Faridabad, Guntur, Gurugram, Jaipur, Kanpur, Pune, Kolhapur, Surat, Vijayawada, Eluru, Ajmer, Visakhapatnam, Bodhgaya, Varanasi, Prayagraj, Agra, Mathura, Dhanbad, Gandhinagar, Udaipur, and Vadodara. The main objective of these super highways is to reduce the travel time between the major cities of India, running roughly along the perimeter of the country. The North–South corridor linking Srinagar (Jammu and Kashmir) and Kanyakumari (Tamil Nadu), and East–West corridor linking Silchar (Assam) and Porbandar (Gujarat) are additional projects. These highway projects are implemented by the National Highway Authority Of India (NHAI). At 5,846 kilometres (3,633 mi), it is the largest highway project in India and the fifth longest in the world. It is the first phase of the National Highways Development Project (NHDP), and consists of two, four, and six-lane express highways, built at a cost of 600 billion (US$7.5 billion). The project was planned in 1999, launched in 2001, and was completed in July 2013.

The Golden Quadrilateral project is managed by the National Highways Authority of India (NHAI) under the Ministry of Road, Transport and Highways. The vast majority of the system is not access controlled, although safety features such as guardrails, shoulders, and high-visibility signs are in use. The Mumbai–Pune Expressway, the first controlled-access toll road to be built in India, is a part of the GQ Project but not funded by NHAI, and is separate from the old Mumbai–Pune section of National Highway 48 (India). Infrastructure Leasing & Financial Services (IL&FS) has been one of the major contributors to the infrastructural development activity in the GQ project.[not verified in body]

History and costs

The Golden Quadrilateral Project (GQ Project) was intended to establish faster transport networks between major cities and ports, provide smaller towns better access to markets, reduce agricultural spoilage in transport, drive economical growth, and promote truck transport.[citation needed]

Prime Minister Atal Bihari Vajpayee laid the foundation stone for the project on 6 January 1999. It was planned to be completed by 2006, but there were delays due to land acquisition constraints and disputes with contractors which had to be renegotiated. In January 2012, India announced the four-lane GQ highway network as complete.

India's government had initially estimated that the Golden Quadrilateral project would cost 600 billion (US$7.5 billion) at 1999 prices. However, the highway was built under-budget. As of August 2011, the cost incurred by the Indian government was about half of the initial estimate, at 308.58 billion (US$3.9 billion). The eight contracts in progress, as of August 2011, were worth 16.34 billion (US$200 million).[needs update]

In September 2009, it was announced that the existing four-laned highways would be converted into six-lane highways. Sections of NH 2, NH 4, NH 5 and NH 8 were prioritized for widening to six lanes under DBFO (Design, Build, Finance, Operate) pattern and more sections would be six-laned in the future. On NH 8, six-lane work was completed from Vadodara to Surat.[when?][citation needed]

No. Segment Length Completed Source
1. Delhi–Kolkata 1,453 km (903 mi) 31 August 2011 [5] Archived 1 August 2009 at the Wayback Machine
2. Chennai–Mumbai 1,290 km (800 mi) 31 August 2011 [6] Archived 4 August 2009 at the Wayback Machine
3. Kolkata–Chennai 1,684 km (1,046 mi) 31 May 2013 [7] Archived 23 July 2009 at the Wayback Machine
4. Mumbai–Delhi 1,419 km (882 mi) 31 August 2011 [8] Archived 28 June 2009 at the Wayback Machine
Total 5,846 km (3,633 mi) 31 May 2013 [9] Archived 29 November 2009 at the Wayback Machine

Route

Only National Highways are used in the Golden Quadrilateral. The four legs use the following National Highways (new numbering system):

  • Delhi – Kolkata: NH 44 from Delhi to Agra & NH 19 from Agra to Kolkata
  • Delhi – Mumbai – Chennai: NH 48
  • Kolkata – Chennai: NH 16

Connected cities

Delhi–Kolkata Kolkata–Chennai Chennai–Mumbai Mumbai–Delhi

Length in each state

The completed Golden Quadrilateral passes through 12 states and a union territory:

Corruption allegations

In August 2003, Jharkhand-based project director Satyendra Dubey, in a letter to the prime minister, outlined a list of bad faith (mala fide) actions in a segment of a highway in Bihar. Dubey's claims included that big contractors had inside information from NHAI officials, that the contractors for this stretch were not executing the project themselves (as stipulated in the contract) but had been subcontracting the work to small builders who lacked technical expertise, and that no follow-up was performed after awarding advances. Dubey's name was leaked by the prime minister's office to the NHAI, and he was transferred against his wishes to Gaya, Bihar, where he was murdered on 27 November.

The NHAI eventually admitted that Dubey's allegations were substantiated, and implemented "radical reforms" in the selection and contract procedures. After considerable Central Bureau of Investigation scrutiny, Mantu Kumar and three accomplices were arrested and charged with murder. Mantu escaped from court on 19 September 2005, but was recaptured a month later. In 2010, Mantu and two others were convicted of murder and other offenses and sentenced to life in prison.

See also

Similar rail development
Similar roads development
Similar ports and river transport development
Similar air transport development
Highways in India
General

This page was last updated at 2023-12-12 02:27 UTC. Update now. View original page.

All our content comes from Wikipedia and under the Creative Commons Attribution-ShareAlike License.


Top

If mathematical, chemical, physical and other formulas are not displayed correctly on this page, please useFirefox or Safari